This workbook goes with the NZES Take-Off Challenge. If you’ve had a go at the challenge, you’ve already done what estimators do every day: read a plan and turn it into quantities.
Here we walk through the same deck, one question at a time. For each step you’ll see what to work out, why an estimator does it that way, and how to do the maths. Then you can try a second deck on your own.
| 3 | What a take-off is, and the golden rules |
| 4 | Reading the plan |
| 5 | Step 1: Deck area · Step 2: Decking boards |
| 6 | Step 3: Joists · Step 4: Piles |
| 7 | Step 5: Concrete · Step 6: Screws |
| 8 | The finished take-off sheet, and common mistakes |
| 9 | From quantities to a price |
| 10 | Try it yourself, and where to go next |
A take-off (or “quantity take-off”) is a list of everything needed to build something, measured from the drawings. It’s the first job on every estimate. Get the quantities wrong and every price that follows is wrong too.
Builders do take-offs to quote. Estimators and quantity surveyors do them for a living, on everything from a deck to a hospital. The method is the same at every size: read the drawing, measure each item in the right unit, show your working, and check it.
| Read the whole plan first | Notes and specs change the answer. “Piles @ 1200 max crs” is as important as the 6000 dimension. |
| Work in one unit | Drawings are in millimetres. Convert to metres before you multiply areas and volumes, or you’ll be out by a factor of a million. |
| Measure, don’t guess | Every number on your sheet should trace back to a dimension or note on the plan. |
| Round up at the end, not the middle | Keep the decimals while you calculate. Round to whole items only when you count what to order. |
| Mind the fence posts | Spacing gives you gaps. The number of members is gaps + 1. (More on page 6.) |
| Waste is separate | Take off the net quantity, then add waste as its own line, so anyone checking can see both. |
| Check it a second way | e.g. 21 boards × 6.0 m = 126 lm, and 18 m² ÷ 0.145 m = 124 lm. Close enough to trust. |
| Decking | 140×32 H3.2 pine, 5 mm gaps, boards run the full 6.0 m length. |
| Joists | 140×45 H3.2 @ 450 crs, 3.0 m long, across the bearers. |
| Bearers | 3 lines (B1–B3) @ 1500 crs, each 6.0 m long. |
| Piles | 125 sq H5 @ 1200 max crs along each bearer, a pile at each end. |
| Footings | 400 × 400 × 500 deep concrete, one per pile. Assume one 20 kg bag of premix makes 0.01 m³. |
| Fixings | 2 decking screws per board at every joist. |
What: the size of the deck surface in square metres (m²).
What: how many 6.0 m boards to order.
What: how many joists at 450 mm centres along the 6.0 m length.
What: how many piles hold up the three bearers.
What: how many 20 kg bags of premix for the pile footings.
What: how many screws to fix the decking down.
This is what the estimator hands on. Every line has a description, a quantity, a unit and the working, so anyone can check it.
| Item | Working | Qty | Unit |
|---|---|---|---|
| Deck area (check) | 6.0 × 3.0 | 18 | m² |
| Decking 140×32 H3.2, 6.0 m | 3000 ÷ 145 = 20.7 → 21 | 21 | lengths |
| Joists 140×45 H3.2, 3.0 m | 6000 ÷ 450 = 13.3 → 14 gaps + 1 | 15 | no. |
| Bearers, 6.0 m | 3 lines × 6.0 m | 18 | lm |
| Piles 125 sq H5 | (6000 ÷ 1200 + 1) × 3 | 18 | no. |
| Footing concrete, 20 kg bags | 0.4 × 0.4 × 0.5 = 0.08 m³ → 8 bags × 18 | 144 | bags |
| Decking screws | 21 × 15 × 2 | 630 | no. |
| Waste allowance | e.g. 2 spare boards, 1 box of screws | – | separate line |
A full take-off would also list joist hangers or fixings, bearer-to-pile connections, any steps, edge boards and finishes. We’ve kept this one to the six challenge questions.
| 14 joists instead of 15 | Forgot the fence-post rule. Gaps + 1. |
| Boards divided by 140, not 145 | Forgot the gap. Gives 21.4 → 22 boards, one too many. |
| Mixing mm and m | 400 × 400 × 500 = 80,000,000 mm³. Convert first: 0.08 m³. |
| Counting piles on one bearer only | Read the note: “along each bearer”. 6 × 3, not 6. |
| Rounding in the middle | Round 20.7 rows up to 21 boards, but don’t round 0.08 m³ to 0.1 before multiplying. |
| Burying waste in the quantity | Keep net and waste apart so the quote can be checked and adjusted. |
Quantities are half the job. The next step is putting a rate against each line. A rate is the cost of one unit of an item, installed. Quantity × rate = the cost of that line, and the lines add up to the price.
| Materials | The supplier’s price per unit, plus delivery. |
| Waste | Offcuts, damage, the bag that split. Usually a percentage, kept visible. |
| Labour | How long it takes × the hourly charge-out rate. Productivity rates (“how many piles can two people set in a day?”) come from experience and records. |
| Plant and hire | Auger, mixer, skip, scaffold. |
| Overheads and margin | The cost of running the business, plus profit. |
| Item | Qty | Unit | Rate | Total |
|---|---|---|---|---|
| Decking 140×32 H3.2, 6.0 m | 21 | lengths | your rate | qty × rate |
| Joists 140×45 H3.2, 3.0 m | 15 | no. | your rate | qty × rate |
| Piles 125 sq H5 | 18 | no. | your rate | qty × rate |
| … | ||||
| Subtotal + margin | the price |
This is where trade experience pays off. You already know roughly how long a job takes and what goes wrong on site. That knowledge is exactly what makes a good rate, and why tradies often make strong estimators.
Same method, different deck. Use the same specs as page 4, with these changes:
| Item | Your working | Your answer |
|---|---|---|
| Deck area (m²) | ||
| Decking boards | ||
| Joists | ||
| Piles | ||
| Concrete (bags) | ||
| Screws |
Answers: 12 m² · 18 boards · 12 joists · 15 piles · 120 bags · 432 screws
Reading plans, measuring quantities and building up rates is the daily work of estimators and quantity surveyors, and NZ construction needs more of them. The NZES Full Estimating & Surveying Certificate teaches it properly, on real projects. Study is self-paced, with one-to-one support from a Senior Quantity Surveyor, so you can learn while you keep working.