How to Do a Deck Take-Off: Free Step-by-Step Guide (NZ)

60003000 FREE WORKBOOK How to Take Off a Deck The Take-Off Challenge, worked step by step: what an estimator does, why, and how. nzes.ac.nz
Deck take-off workbook
NZES

Welcome

This workbook goes with the NZES Take-Off Challenge. If you’ve had a go at the challenge, you’ve already done what estimators do every day: read a plan and turn it into quantities.

Here we walk through the same deck, one question at a time. For each step you’ll see what to work out, why an estimator does it that way, and how to do the maths. Then you can try a second deck on your own.

What’s inside

3What a take-off is, and the golden rules
4Reading the plan
5Step 1: Deck area · Step 2: Decking boards
6Step 3: Joists · Step 4: Piles
7Step 5: Concrete · Step 6: Screws
8The finished take-off sheet, and common mistakes
9From quantities to a price
10Try it yourself, and where to go next

How to use it

  • Keep the plan on page 4 open while you work.
  • Use a calculator. Estimators do.
  • Write your working down. A number without working can’t be checked, and a take-off that can’t be checked can’t be trusted.
A note on the drawing. The deck in this workbook is a training exercise. Member sizes and spacings are given so you can practise measuring, not as a design. Real decks need to meet NZS 3604 and your council’s requirements.
2
Deck take-off workbook
NZES

What is a take-off?

A take-off (or “quantity take-off”) is a list of everything needed to build something, measured from the drawings. It’s the first job on every estimate. Get the quantities wrong and every price that follows is wrong too.

The plandrawings + specs Quantitiesthe take-off Ratesmaterials, labour The pricequote or estimate THIS WORKBOOK

Builders do take-offs to quote. Estimators and quantity surveyors do them for a living, on everything from a deck to a hospital. The method is the same at every size: read the drawing, measure each item in the right unit, show your working, and check it.

The golden rules

Read the whole plan firstNotes and specs change the answer. “Piles @ 1200 max crs” is as important as the 6000 dimension.
Work in one unitDrawings are in millimetres. Convert to metres before you multiply areas and volumes, or you’ll be out by a factor of a million.
Measure, don’t guessEvery number on your sheet should trace back to a dimension or note on the plan.
Round up at the end, not the middleKeep the decimals while you calculate. Round to whole items only when you count what to order.
Mind the fence postsSpacing gives you gaps. The number of members is gaps + 1. (More on page 6.)
Waste is separateTake off the net quantity, then add waste as its own line, so anyone checking can see both.
Check it a second waye.g. 21 boards × 6.0 m = 126 lm, and 18 m² ÷ 0.145 m = 124 lm. Close enough to trust.
3
Deck take-off workbook
NZES

Reading the plan

B1B2B3 JOISTS @ 450 CRSTYP. FULL LENGTH PILES @ 1200 MAX CRSALONG EACH BEARER DECKING RUNS THIS WAY 6000 3000 1500 1500 1200 PLAN · NTS · DIMS IN MM
Plan · not to scale · dimensions in millimetres. Training exercise, not a design.

The notes

Decking140×32 H3.2 pine, 5 mm gaps, boards run the full 6.0 m length.
Joists140×45 H3.2 @ 450 crs, 3.0 m long, across the bearers.
Bearers3 lines (B1–B3) @ 1500 crs, each 6.0 m long.
Piles125 sq H5 @ 1200 max crs along each bearer, a pile at each end.
Footings400 × 400 × 500 deep concrete, one per pile. Assume one 20 kg bag of premix makes 0.01 m³.
Fixings2 decking screws per board at every joist.

Words you’ll see on drawings

crs centres: measured from the middle of one member to the middle of the next.
max crs the spacing can be less, never more.
TYP. typical: what’s shown applies to all the others too.
H3.2 / H5 timber treatment levels. H5 is for in-ground use, like piles.
NTS not to scale: use the written dimensions, never a ruler.
lm lineal (linear) metres.
4
Deck take-off workbook
NZES

Area and decking

Step 1

Deck area

What: the size of the deck surface in square metres (m²).

Why: area is the quick check for everything else. Decking, stain and oil, and labour are often priced or sanity-checked per m². If a later number doesn’t fit the area, something’s wrong.
Convert mm to m6000 mm = 6.0 m · 3000 mm = 3.0 m
Length × width6.0 × 3.0
Deck area18 m²
Step 2

Decking boards

What: how many 6.0 m boards to order.

Why it’s done this way: boards are bought by the length, not by the m². Each board covers its own width plus one gap. Forget the gap and you’ll order too many; forget that the last row is still a full board and you’ll order too few.
joist 145 mm cover 140 board 5 gap
Cover per board140 + 5 = 145 mm
Rows across the 3.0 m width3000 ÷ 145 = 20.7
Round up (a part row is still a board)21 rows
Boards run the full 6.0 m, one per row21 × 1
Decking21 boards (126 lm)
Estimator’s habit: order 1–3 spare boards for splits, bows and offcuts. Write it as a separate waste line so the net quantity stays visible.
5
Deck take-off workbook
NZES

Joists and piles

Step 3

Joists

What: how many joists at 450 mm centres along the 6.0 m length.

Why it trips people up: dividing by the spacing gives you the number of gaps, not members. Like fence posts, there’s always one more joist than there are gaps.
gap 1gap 2gap 3gap 4 4 gaps → 5 joists. Always gaps + 1.
Gaps along 6.0 m6000 ÷ 450 = 13.3
Round up (spacing is a maximum)14 gaps
Fence-post rule14 + 1
Joists15 joists (15 × 3.0 m = 45 lm)
Step 4

Piles

What: how many piles hold up the three bearers.

Why: piles are counted one bearer at a time. Same fence-post rule: there’s a pile at each end of each bearer.
B1B2B3 6 piles6 piles6 piles 1200
Gaps along one 6.0 m bearer6000 ÷ 1200 = 5
Piles per bearer (gaps + 1)6
Three bearers6 × 3
Piles18 piles
6
Deck take-off workbook
NZES

Concrete and screws

Step 5

Concrete

What: how many 20 kg bags of premix for the pile footings.

Why: concrete is a volume (m³). Work out one footing, multiply by the number of piles, then convert to what you’ll actually buy: bags, or a ready-mix truck.
400400500deep pile
One footing (in metres)0.4 × 0.4 × 0.5 = 0.08 m³
Bags per footing (0.01 m³ each)0.08 ÷ 0.01 = 8
18 piles18 × 8
Concrete144 bags (1.44 m³)
Estimator’s judgement: 144 bags is a lot of mixing. At this size most would price about 1.5 m³ of ready-mix instead and compare the two. Knowing when to switch is part of the job. Bag yields vary by brand, so check the bag.
Step 6

Decking screws

What: how many screws to fix the decking down.

Why: fixings are counted at every place a board crosses a joist. Boards × joists gives you the crossings; the spec tells you how many screws at each.
Crossings21 boards × 15 joists = 315
2 screws at each315 × 2
Screws630 screws
7
Deck take-off workbook
NZES

The finished take-off

This is what the estimator hands on. Every line has a description, a quantity, a unit and the working, so anyone can check it.

ItemWorkingQtyUnit
Deck area (check)6.0 × 3.018m²
Decking 140×32 H3.2, 6.0 m3000 ÷ 145 = 20.7 → 2121lengths
Joists 140×45 H3.2, 3.0 m6000 ÷ 450 = 13.3 → 14 gaps + 115no.
Bearers, 6.0 m3 lines × 6.0 m18lm
Piles 125 sq H5(6000 ÷ 1200 + 1) × 318no.
Footing concrete, 20 kg bags0.4 × 0.4 × 0.5 = 0.08 m³ → 8 bags × 18144bags
Decking screws21 × 15 × 2630no.
Waste allowancee.g. 2 spare boards, 1 box of screws–separate line

A full take-off would also list joist hangers or fixings, bearer-to-pile connections, any steps, edge boards and finishes. We’ve kept this one to the six challenge questions.

Common mistakes

14 joists instead of 15Forgot the fence-post rule. Gaps + 1.
Boards divided by 140, not 145Forgot the gap. Gives 21.4 → 22 boards, one too many.
Mixing mm and m400 × 400 × 500 = 80,000,000 mm³. Convert first: 0.08 m³.
Counting piles on one bearer onlyRead the note: “along each bearer”. 6 × 3, not 6.
Rounding in the middleRound 20.7 rows up to 21 boards, but don’t round 0.08 m³ to 0.1 before multiplying.
Burying waste in the quantityKeep net and waste apart so the quote can be checked and adjusted.
8
Deck take-off workbook
NZES

From quantities to a price

Quantities are half the job. The next step is putting a rate against each line. A rate is the cost of one unit of an item, installed. Quantity × rate = the cost of that line, and the lines add up to the price.

What goes into a rate

MaterialsThe supplier’s price per unit, plus delivery.
WasteOffcuts, damage, the bag that split. Usually a percentage, kept visible.
LabourHow long it takes × the hourly charge-out rate. Productivity rates (“how many piles can two people set in a day?”) come from experience and records.
Plant and hireAuger, mixer, skip, scaffold.
Overheads and marginThe cost of running the business, plus profit.

Lay it out like this

ItemQtyUnitRateTotal
Decking 140×32 H3.2, 6.0 m21lengthsyour rateqty × rate
Joists 140×45 H3.2, 3.0 m15no.your rateqty × rate
Piles 125 sq H518no.your rateqty × rate
…
Subtotal + marginthe price
Why we haven’t printed prices: timber and concrete prices move every few months and vary by region and supplier. A real estimate uses current quotes. The method on this page never changes.

This is where trade experience pays off. You already know roughly how long a job takes and what goes wrong on site. That knowledge is exactly what makes a good rate, and why tradies often make strong estimators.

9
Deck take-off workbook
NZES

Try it yourself

Same method, different deck. Use the same specs as page 4, with these changes:

Deck size4800 × 2500 mm
Decking140×32, 5 mm gaps, 4.8 m lengths running the long way
Joists@ 450 crs, 2.5 m long
Bearers3 lines, each 4.8 m long
Piles@ 1200 max crs along each bearer
Footings and screwsAs before: 8 bags per footing, 2 screws per crossing
ItemYour workingYour answer
Deck area (m²)
Decking boards
Joists
Piles
Concrete (bags)
Screws

Answers: 12 m² · 18 boards · 12 joists · 15 piles · 120 bags · 432 screws

Enjoyed this? You might make a good estimator.

Reading plans, measuring quantities and building up rates is the daily work of estimators and quantity surveyors, and NZ construction needs more of them. The NZES Full Estimating & Surveying Certificate teaches it properly, on real projects. Study is self-paced, with one-to-one support from a Senior Quantity Surveyor, so you can learn while you keep working.

Want another go, or to send it to a mate on the tools?