A take-off is how an estimator turns a plan into a list of quantities to price. The challenge above uses a 6.0 × 3.0 m timber deck with three bearer lines, joists at 450 centres and piles at 1200 maximum centres. Here’s the method for each of the six quantities. Try the question first, then open the worked answer.
Step 1
How do you work out the area of a deck?
Multiply the length by the width, after converting millimetres to metres. Plans are dimensioned in millimetres, so 6000 mm becomes 6.0 m. Area is the first number on most take-offs because everything else is checked against it.
Show the worked answer for this deck
- 6000 mm = 6.0 m and 3000 mm = 3.0 m
- 6.0 × 3.0 = 18 m²
Step 2
How many decking boards do I need?
Work out how much width each board covers, which is the board width plus one gap. Divide the deck width by that cover and round up, because you can’t buy part of a row. If the boards run the full length of the deck, each row is one board.
Show the worked answer for this deck
- Cover per board: 140 mm board + 5 mm gap = 145 mm
- 3000 ÷ 145 = 20.7, round up to 21 rows
- Boards run the full 6.0 m, so one board per row: 21 boards
- Most estimators order 1 to 3 spare for offcuts and bad boards
Step 3
How many joists does a deck need?
Divide the length the joists are spread along by the joist spacing (the centres), round up to get the number of gaps, then add one. That extra joist is the fence-post rule: there is always one more post than gaps. Forgetting it is the most common take-off mistake.
Show the worked answer for this deck
- 6000 ÷ 450 = 13.3, round up to 14 gaps
- Joists = gaps + 1 (the fence-post rule)
- 15 joists (the most common wrong answer is 14)
Step 4
How many piles does a deck need?
Do one bearer line first. Divide its length by the maximum pile spacing, round up to get the gaps, and add one so there is a pile at each end. Then multiply by the number of bearer lines.
Show the worked answer for this deck
- One bearer: 6000 ÷ 1200 = 5 gaps, so 6 piles
- 3 bearer lines × 6 piles = 18 piles
Step 5
How much concrete do I need for deck piles?
Work out the volume of one footing in cubic metres (length × width × depth), multiply by the number of footings, then convert to bags using the yield printed on the bag. Always convert millimetres to metres before multiplying.
Show the worked answer for this deck
- One footing: 0.4 × 0.4 × 0.5 = 0.08 m³
- 0.08 m³ ÷ 0.01 m³ per 20 kg bag = 8 bags per footing
- 18 footings × 8 = 144 bags
- At this volume (1.44 m³), many estimators would price ready-mix instead of bags
Step 6
How many decking screws do I need?
Every board crosses every joist, and each crossing gets a set number of screws. Multiply boards by joists to get the crossings, then multiply by the screws per crossing.
Show the worked answer for this deck
- 21 boards × 15 joists = 315 crossings
- 315 × 2 screws = 630 screws
- Buy a box extra for dropped and broken screws
Want every step with diagrams, the finished take-off sheet and how to turn quantities into a price? Read the free deck take-off guide.
What is a take-off in construction?
A take-off is the list of every material and quantity needed to build something, measured from the drawings. Estimators and quantity surveyors do a take-off first, then apply rates to turn the quantities into a price.
Why does the deck need 15 joists and not 14?
Because of the fence-post rule. 6000 mm at 450 mm centres gives 14 gaps, and you need a joist at both ends of every gap, so there is always one more joist than gaps.
Should I add waste to a decking order?
Usually, yes. Estimators allow for offcuts, damaged boards and fixings that go missing. How much depends on the layout and board lengths, so in this challenge we count the exact quantity and note the spares separately.
What do H3.2 and H5 mean on a deck plan?
They are New Zealand timber treatment hazard classes. H3.2 is for timber above ground but exposed to the weather, like decking and joists. H5 is the higher level used for piles that go into the ground and carry the structure.
Is this deck designed to NZS 3604?
No. The sizes and spacings are given for the exercise, not as a design. A real deck needs to meet NZS 3604 and your council’s requirements.
How do I become an estimator or quantity surveyor in New Zealand?
Many estimators start on the tools. A trade background is a real advantage because you already know how things go together. What you need to add is the method: measuring from drawings, building up rates and pricing work. NZES teaches this online in the Full Estimating & Surveying Certificate. See the Full Certificate.